Costly Navy Frigate Cited by Lawmakers for ‘Significant’ Risks

 

 

 

Bloomberg

 

By

Anthony Capaccio

8 de diciembre de 2020 20:19 CET

  •  

Defense policy bill directs Navy to build land-test facility

  •  

Fincantieri was awarded the frigate contract earlier this year

 

 

 

 

An artist’s rendering of Fincantieri’s frigate.

 

Source: Fincantieri

 

House and Senate defense lawmakers say the Navy’s new frigate program faces “significant risks” amid a surge in cost estimates for the next-generation vessel built by the American unit of Fincantieri SpA.

The latest in global politics

Get insight from reporters around the world in the Balance of Power newsletter.

Principio del formulario

Final del formulario

In language in the National Defense Authorization Act being voted on this week, lawmakers cited the need for “cost realism” in the frigate program and the potential risks involved in shifting to “predominantly U.S. component suppliers instead of the mainly foreign suppliers used in the parent vessel design.” They also flagged a complex propulsion drive train “that has not previously been used” on U.S. Navy ships.

“A strong technical foundation for this program is critically important,” according to the report, which cited the key role the frigate is expected to play for the Navy “for many decades.”

The Navy is counting on an affordable frigate as a key component in its effort to meet President Donald Trump’s goal of having 355 deployable ships by 2035, up from about 299 today. Then-Defense Secretary Mark Esper set an even more ambitious goal in October of a 500-ship Navy by 2045. That effort would include unmanned vessels of unknown weight, capabilities and cost.

Both of those goals are likely to be heavily scrutinized by the incoming Biden administration after it takes office Jan. 20.

The Congressional Budget Office warned in an October report that the first 10 vessels in the frigate contract, awarded this year, may cost $12.3 billion, or 40% more than the service calculated.

Congress Eyes a One-Week Spending Bill to Avert Shutdown

As a result, the program will be at center of the broader battle over the appropriate level of funding for Navy shipbuilding in the fiscal 2022 five-year defense plan. General Mark Milley, chairman of the Joint Chiefs of Staff, last week said that the plan will require some “bloodletting.”

The CBO assessment projected the frigates will cost an average of $1.2 billion apiece in inflation-adjusted dollars. That’s in contrast to the Navy’s estimate of $870 million each for a vessel billed as a more versatile and better-armed replacement for the troubled Littoral Combat Ship. After years of cost overruns, the beleaguered LCS program was truncated because of its mechanical flaws, light armament and vulnerability to attack.

Lawmakers referenced the LCS program’s problems in requiring the Navy to set up a land-based facility to test new technology before installation.

The primary objective of the land test facility “shall be to demonstrate across the full range of engineering plant operations” to include the full propulsion drive train, lawmakers wrote.